To Analyze the Factors Affecting Downtime of Ready Mix Concrete Plant with the help of RII Method

Authors

  • Suwarnkar S PG- Schelor- Civil [C & M], D Y Patil Institute of Engineering & Technology, Ambi. Pune.Savitribai Phule Pune University, Pune.
  • Saharkar U Asst Professor, D Y Patil Institute of Engineering & Technology, Ambi. Pune.Savitribai Phule Pune University, Pune.

Keywords:

Downtime, Concrete Plant

Abstract

In Ready Mix Concrete we produce a Concrete for Construction Projects. Downtime is any moment when there is no machine in manufacturing. In order to help define trends in machine efficiency, downtime can be classified. As equipment failures and breakdowns are extremely noticeable, it gets a high amount of attention. To determine the factors causes for downtime or slow production of concrete plant along with mathematical model to find its downtime cost through case study. In this paper we are planning to conduct a survey to collect the data from various concrete plants so we design a simple questioner to conduct this survey. Relative Importance Index is a method use to find out the important factors and then we provide the rank for these factors. In this paper we also suggest the simple Maintenance log book for concrete plant

References

Bostjan Gomiscek, Damjan Maletič at.el. ,”The role of maintenance in improving company’s competitiveness and profitability: A case study in a textile company”, Journal of Manufacturing Technology Management, Vol. 25, No. 4, pp.441 - 456

Aadal hamid, fard ali bagheri, rad kiyanoosh golchin, al. Et., “impact of plants and equipment management in construction industry of iran”, research journal of applied sciences, engineering and technology 7(11): 2371-2375, 2014 doi:10.19026/rjaset.7.538 issn: 2040-7459; e-issn: 2040- 7467 © 2014

Chodwadia niraj, pimplikar sunil “downtime cost of construction equipment”. K.s.r. college of engineering, tiruchengode tamil nadu icsee feb. 2011

Gangane kalpana, patil dipak “downtime cost of equipment used in a construction industry” international journal on future revolution in computer science & communication engineering issn: 2454-4248volume: 3 issue: 12, page no.271 – 277

Manikandan m., prof. Adhiyaman m., dr.pazhani k. C., “a study and analysis of construction equipment management used in construction projects for improving productivity” international research journal of engineering and technology (irjet) volume: 05 issue: 03 |

mar-2018 e-issn: 2395-0056 p-issn: 2395-0072.

Naskoudakis Ilias, Petroutsatou Kleopatra, “A Thematic Review of he Main Research on Construction Equipment over Recent Years” Periodica Polytechnica Architecture 47(2), pp. 110-118, 2016 DOI: 10.3311/PPar.10384 Creative Commons Attributionb research article Received 09 December 2016.

Phadatare D. B., Charhate S. B., “Impact Of Construction Equipment’s On Building Site Productivity”, International Journal of Civil Engineering and Technology (IJCIET) Volume 7, Issue 4, July-August 2016, pp. 513–520 Article ID: IJCIET_07_04_047 Available online.

Fuerst Michael, Vorster Michael, Hicks Donald “A Model for Calculating Cost of Equipment Downtime and Lack of Availability in Directorates of Engineering and Housing” USACERL TECHNICAL REPORT P-91/16 March 1991.

Poonam P. Patil, Rohit R. Salgude, “Determination of Downtime Cost of Ready-Mix Concrete Plant and Transit Mixer”, International Journal of Innovative Technology and Exploring Engineering (IJITEE) ISSN: 2278-3075, Volume-8 Issue-9, July 2019.p.p.- 3105-3108.

Juraj drahňovský,” equipment categorization as a basis to improve the organization of maintenance”, 10.2478/v10186-012-0008-3 2012, volume 20, special number, p.p- 21-25

Karthik Prabhu.R 1, Sampath Kumar.K,” A Review On Factors Involved In Equipment Quality And Management In Ready Mix Concrete”, International Research Journal Of Engineering And echnology (Irjet), Volume: 05 Issue: 02 | Feb-2018, E-Issn: 2395-0056, P.P.-577-581

Downloads

Published

2020-07-30

How to Cite

Suwarnkar, S., & Saharkar, U. R. (2020). To Analyze the Factors Affecting Downtime of Ready Mix Concrete Plant with the help of RII Method. Universal Research Reports, 7(8), 1–8. Retrieved from https://urr.shodhsagar.com/index.php/j/article/view/870

Issue

Section

Original Research Article